19.3. - 6.7.2018.

Section Zaprešić - Krapina

In the period from 19.3. to 6.7.2018. extraordinary maintenance works will be performed that include asphalt construction repair and the facilities according to the plan as follows:

Asphalt construction repair ( direction to Zagreb):


08.05. - 21.06. km 24+350 to km 25+450
03.05. - 06.07. km 12+500 to km 15+500

Facilities rehabilitatio:

20.03. -21.06. bridge Vrbna in km 34+700 (both direction)
20.03. -21.06. bridge Šemnica in km 37+050 (both direction)
21.03. - 21.06. overpass in the intechange Krapina in km 42+700