Works on the motorway sections - information

Section Zaprešić - Zabok

In the period from 15.09. to 15.11.2021 rehabilitation works of the LK Conec bridge at km 19 + 270 (direction Zagreb) will be performed.
During the works, the traffic will take place in two directions on the opposite side of the highway in accordance with the temporary traffic regulation.

Section Zabok - Sveti Križ Začretje

In the period from 21.09. to 29.10.2021. rehabilitation works of the overpass at the Sveti Križ Začretje intersection will ) will be performed.
Traffic will be regulated by temporary traffic signalization.

Section Đurmanec - Trakošćan

In the period from 14.09. to 30.11.2021 reconstruction of the road structure on the section from km 54 + 960 to km 57 + 355 in the direction of Zagreb will be carried out.
During the works, the traffic will take place in two directions on the opposite side of the highway in accordance with the temporary traffic regulation.